Clarification Notice
Clarification of Request for Application (IFA No. 03/NTA/2073/74) of the
“Re-Invitation for Application to Build District Optical Fiber Network and Provide Optical
Network Lease Connectivity Services in Province no. 6 & 7 ”
S.No. |
Queries |
Response |
1 |
It seems we need joint points in some places. Please clearify the equipments that need to put in joint points | These are fiber splicing nodes that can be present in every 2 Km and major junctions or settlements. These are fiber optic joint/splice encloser placed outdoor. |
2 |
NTA has mentioned regards DWDM types and its quantity but not specified the place. Please clearify the places and reason of putting specific DWDM. | See Attached. |
3 |
In Type 1,2,3 and 4 DWDM, NTA has specified for 10G line card. It is not recommended to run 10G and 100G service in same fiber. It should be 100G for line card. | Noted. |
4 |
Service Matrix has not been provided yet. | Its applicant’s responsibility to prepare service matrix. |
5 |
NTA has mentioned ring protection for data network but has not mentioned about core protection. | It’s the operators responsibility to ensure core protection. |
6 |
In IP Ring Network, router to router connection is not possible for 100G as distance is too long. Router should be connected to DWDM and DWDM carries the traffic. | Noted. |